Basement Remodel

Project details

materials: Thomasville cherry cabinetry and granite provided by Home Depot. Kohler shower stall, glass shower door, Moen shower valve and vanity faucets, Kohler toilet and bathroom hardware provided by Home Depot. Millwork including doors, trim and wainscoting provided by Trim & More.

time to completion: This basement took 5 weeks to complete. Framing and mechanical rough ins including plumbing, electrical, and HVAC runs were completed within 2 weeks. Drywall was completed in the third week. Tile, trim, cabinetry and painting was completed in the last two weeks of this job. Granite fabrication and installation follows for final touches to this entertainment room.